Phase 1 of the Kentwood Farm section of the North Wokingham Strategic development Location has been given the
name of Mulberry Grove by the developers, Crest Nicholson, in recognition of the local silk industry in times
past.
The first houses went on sale in 2015 and the site is now complete.
Phase 2 of this development, Called Mulberry View, was granted planning approval in May 2017 and work is now in
progress to deliver some 225 dwellings on the site.
The first phase of development at the eastern end, called Emmbrook Place, started in 2015, with houses coming up
for occupation by October 2016, and is nearly finished. A second phase of houses built by Bovis is now under
way.
Linden Homes have acquired the north-west area of the development from Bovis and the first phase, called Copsewood,
is now partially completed.
Plans have also been approved for two further phases. The Society’s representatives have been in active discussion
with Linden Homes about design and infrastructure issues.
A combined primary and nursery school, called St Cecilia's Church of England Primary School, opened in September
2022.The future of the proposed community centre has been thrown into uncertainty after the king’s Church withdrew
its offer to manage it.
A consortium including Bellway and Shanly Homes submitted an application in 2015 to build 300 dwellings to the
east of the assigned North Wokingham Strategic Development Location. The developers said that this approximated to
the shortfall in the SDL itself and that it would have the benefit of delivering that part of the North Wokingham
Distributor Road earlier and at their own expense.
The Society’s Executive Committee submitted a response to this application, which it urged should be rejected as an
overdevelopment of the area, taking way an important area of open space for local residents and closing the green
gap between Wokingham and Bracknell. We also objected to the lack of proper consultation with the local community
before the application was made.
At a Meeting on 25 February 2015 the Wokingham Borough Council Planning Committee noted a considerable number of
similar objections, but were reminded that the contribution of that section of the Distributor Road would be a
significant gain and also that a similar application that they rejected had gone to Appeal but was approved by the
Inspector, at considerable cost to the Council. The Committee decided to agree the application as submitted.
Construction started in the Autumn of 2017 and the development is now complete.
In 2016 Berkeley Homes presented a proposal for128 dwellings at Bell Farm, to the north of Bell Foundry Lane
(see plan below), a number not included in the North Wokingham Strategic Development Location proposals agreed by
the Borough Council. This was originally displayed at public consultation on 6 June and met with concerns from
local residents in respect of the unplanned additional numbers and the possibility that, as with Keephatch Beech,
the Council might not be able to reject the application when it is submitted. The developers said that the scheme
would deliver enhancement for the adjacent stretch of the Distributor Road along Bell Foundry Lane and a new
country park within the site.
An application was subsequently submitted and approved by the Borough Planning Committee on 28 October 2016. The
Society’s Executive Committee did not make any submission in view of the similarity of the plans to those submitted
by Bellway and Shanly Homes for Keephatch Beech.
Construction commenced in the Autumn of 2017 and is now complete.
The development is being marketed under the name of Eldridge Park.
In 2016 David Wilson Homes applied for planning permissions to construct one, two, three and four bedroom homes
on Ashridge Farm in Warren House Road.
According to the plans, 53 of the new homes would be affordable and 335 parking spaces and 26 acres of public open
space would be provided on the site.
The developer agreed to sign over part of the land to Wokingham Borough Council, so that a section of the Northern
Distributor Road could be built on it.
The Borough Council is itself the owner of this land and applied in May 2021to build up to 130 residential
units, including 46 affordable homes, and a 70-bed care home on the site. The Society’s Executive Committee
objection to the proposal can be seen here.
The application was due to be considered by the Planning Committee in December 2021 but was withdrawn for further
consideration by the planning officers.
Since then the Borough Council has decided that the cost of building the care home was no longer affordable. The
land assigned to this part of the development may be used for other purposes in due course.
Ashill Development Company has obtained planning permission to build 45 dwellings on the Hewden Plant hire site
off Old Forest Road. The site is being developed in association with Bellway Homes.
The Society’s Executive Committee sent Ashill its pre-application views, and some of these concerns relating to
housing density, scale and massing, design, layout, parking and access were reflected in the amended plans as
submitted. Density was reduced from 50 to 45 dwellings, Maximum heights were reduced from four to three storeys and
all houses were reduced from three to two and a half storeys at most.
Design was amended and improved to propose a more traditional design, including the introduction of traditional
building features to the apartment buildings, such as bay windows. Homes facing the southern boundary were
redesigned as link detached dwellings. A landscape buffer and new softened frontages to street scene were
introduced.
The total number of car parking spaces was increased to 83 and parking areas were broken up with street planting to
reduce impact of hardstanding.
The development has yet to start.
In September and October 2013 the Borough Council consulted on routes for the North Wokingham Distributor Road
(NWDR) and there was a clear public preference for Alternative B above. Further refinements to this route refined
the design detail of Alternative B to take account of these were presented to and agreed by the Council Executive
at the end of September 2015.
The NWDR, now complete, consists of seven separate schemes, five of which were developer led (Bell Farm,
Matthewsgreen, Kentwood Farm, Keephatch Beech and Ashridge Farm) and two delivered by Wokingham Borough Council,
these being West of Old Forest Road (WOFR) and Toutley Road.
The NWDR connects the A329 near the BP garage on Reading Road with the A329(M) Reading to Bracknell motorway near
the Coppid Beech roundabout junction. The new road also provides a link from Winnersh to the A329(M) avoiding
Wokingham town centre.
In addition the NWDR allows access to the new North Wokingham developments and gives these areas a convenient and
direct route to the motorway network via the A329 (M) and the M4.